Reactivate Rejected Report as a Contractor

Reactivate Rejected Report - Contractor

If the report was rejected by the Operator (system owner) the status of this report will change from Submitted to Rejected. 

 

To amend details requested by the operator and submit again open the rejected report and click Reactivate Report

 

A popup message will appear informing the changing of status: moved from Rejected to Reported. Please feel free to add a comment to explain the reason for changing the status. Then click Change Status to confirm. 

 

When moving the status back to Reported first amend the necessary details. Click on the pencil button to be able to edit the report. 

 

After amending the necessary details you will need to accept the report again to submit to the operator (system owner). 

 

Click Accept. A popup message will appear informing you that you are moving the report from Reported to Submitted status. Click Change Status

 

The Operator (system owner) will receive the report again for review and acceptance.